From 25 November 2027
From 25 November 2027, the employer responsible for the asbestos removal and cleaning work will no longer be permitted to appoint the analyst who assesses the area and issues the Certificate for Reoccupation. The change is intended to strengthen independence and impartiality in the four-stage clearance process.
What is changing?
The Control of Asbestos (Amendment etc.) Regulations 2026 will replace regulation 20 of the Control of Asbestos Regulations 2012. Under the new requirement, the person appointing the analyst must ensure that the analyst is appropriately accredited. However, the employer responsible for ensuring the work area has been thoroughly cleaned cannot make that appointment.
Independent appointment
In practice, this means the analyst should be appointed independently of the asbestos removal contractor, normally by the building owner, client or other dutyholder responsible for the project.
When does it take effect?
Although the Regulations were made in November 2026, the new requirement governing the appointment of the clearance analyst takes effect on 25 November 2027. Until then, HSE’s existing guidance remains relevant. HSE already strongly recommends that the analyst used for site-clearance certification is independently sourced and employed by the building owner or client in control of the premises.
What remains the same?
The existing four-stage clearance process remains the technical framework for licensed asbestos-removal projects:
- Preliminary check of site condition and job completeness.
- Thorough visual inspection of the enclosure or work area, airlock and baglock.
- Air monitoring with disturbance of surfaces, where required.
- Final visual assessment after the enclosure has been dismantled.
Contractor and analyst responsibilities
The licensed removal contractor remains responsible for thoroughly cleaning the work area and declaring it visibly clean before the clearance process starts. The analyst’s role is to provide an independent assessment; they should not carry out asbestos clean-up work.
What should dutyholders do now?
Dutyholders planning licensed asbestos removal should review their procurement and project arrangements ahead of the 2027 change. Consider:
- who will appoint the clearance analyst;
- how the appointment will remain independent of the removal contractor;
- whether the analyst’s accreditation has been checked;
- allowing sufficient time for clearance activities in the project programme; and
- documenting the responsibilities of the client, removal contractor, analyst and project manager.
Further guidance
HSE has said it will update its Approved Code of Practice, Managing and working with asbestos (L143), and Asbestos: The Analysts’ Guide (HSG248), as well as providing further support for dutyholders appointing third-party providers.
How Asbestos Compliance can help
Asbestos Compliance can help property teams review asbestos information, scope survey work and clarify project responsibilities before refurbishment, demolition or licensed removal work begins.
Sources
HSE: legislative and guidance proposals for the Control of Asbestos Regulations 2012
Read the HSE consultation outcome →The 2026 Regulations
The Control of Asbestos (Amendment etc.) Regulations 2026
Read the Regulations →HSG248
HSE: Asbestos – The Analysts’ Guide (HSG248)
Read The Analysts’ Guide →